Westwood St Thomas School, Salisbury  
Westwood St Thomas School - Exterior Elevation Westwood St Thomas School - Computer Suite

Westwood St Thomas School - Reception Area

Client and User: Wiltshire County Council

Value: Project Budget               £2,300,000

           Phase 1 contract            £   650,000

           Phase 2 contract            £1,650,000


Date(s): 2002 – 2003 (Phase 1 contract 16 weeks; Phase 2 contract 38 weeks)

  • Project Manager for the refurbishment and extension of existing upper school in Salisbury to facilitate the transition from three-tier to two-tier education system.  Two stage procurement strategy was recommended to meet the programme constraints.

 